Issued for Interns
All Samples Get the Guide
← All Samples

ExAC Section 4 Sample Exam — 10 Free Questions

Section 4 covers project delivery and practice management. The full section has about 130 multiple-choice questions over three hours. Topics include bidding and contractor selection, the CCDC 2 Stipulated Price Contract, construction management delivery models under CCDC 5A and 5B, certificates of payment, change directives, supplemental instructions, site review responsibilities, deficiency management, substantial performance, and professional liability. Many questions present realistic scenarios requiring you to apply a specific contract clause or identify the correct professional response under Canadian construction law.

These ten sample questions reflect the scenario-based format and level of contract detail expected in the full Section 4 exam. Candidates often underestimate this section — it requires precise familiarity with CCDC documents and the Canadian Handbook of Practice, not just a general understanding of how construction projects are managed. After each question, the rationale identifies the relevant contract clause or CHOP reference and explains the correct answer clearly. The full Issued for Interns study guide covers all CCDC contracts in detail, includes CHOP references, and provides complete timed Section 4 mock exams.

Read each scenario the way an examiner writes it — the correct answer usually turns on one specific CCDC clause or CHOP reference. Every question in this sample is written by candidates who sat and passed the ExAC, to give you a sense of what you will face on exam day.

Loading sample questions…
Section 4 sample questions & answer explanations

Here are all ten Section 4 sample questions in full. Read each question, choose your answer, then expand the explanation to see the correct choice and the reasoning behind it — the same detailed rationale included with every question in the full study guide.

  1. Question 1Theme 9

    A heritage restoration project requires a highly specialized flying-buttress consolidation technique that only one contractor in the region is qualified to perform. The owner approaches that contractor directly and negotiates price and terms without a competitive bidding process. Which procurement method does this describe?

    • AOpen (public) tendering
    • BQualification-based selection
    • CInvited (select) tendering
    • DNegotiated contract
    Show answer & explanation

    Correct answer: Negotiated contract

    A negotiated contract is used when the owner deals directly with a single contractor — often because only that firm has the specialized expertise required — without a formal competitive process. This differs from QBS, which is a structured, ranked selection process typically used for professional services with multiple respondents, and from invited tendering, which still involves price competition among a prequalified shortlist.

  2. Question 2Theme 10

    Under CCDC 2, when the Consultant reviews a Contractor's shop drawings, which statement correctly describes the SCOPE and EFFECT of that review?

    • AThe Consultant must approve the shop drawing exactly as submitted or reject the entire submittal
    • BThe review verifies all dimensions, quantities, and fabrication details, transferring responsibility for errors to the Consultant
    • CDesign intent and general arrangement only; the Contractor keeps responsibility for dimensions, quantities and deviations
    • DOnce stamped, the shop drawing supersedes the Contract Documents
    Show answer & explanation

    Correct answer: Design intent and general arrangement only; the Contractor keeps responsibility for dimensions, quantities and deviations

    Shop Drawings is GC 3.8 in the 2020 edition; GC 3.10 is the 2008 numbering and no longer exists. GC 3.8.4 limits the Consultant's review to conformity to the design concept and general arrangement only. GC 3.8.6 confirms the review does not relieve the Contractor of responsibility for errors or omissions in the Shop Drawings or for meeting all requirements of the Contract Documents — under GC 3.8.3 the Contractor has already represented that it verified field measurements and coordinated each Shop Drawing. GC 3.8.5 puts the onus on the Contractor to expressly advise the Consultant in writing of any deviation. The review neither verifies every detail nor amends the Contract Documents.

  3. Question 3Theme 11

    During a site visit on a Construction-Management project, an individual sub-trade worker asks the architect directly to approve a change to how a detail is installed. What is the most appropriate response?

    • ADecline, and route it through the Contractor/CM in writing (RFI or SI)
    • BGive the worker direction on the spot to keep the job moving, then tell the CM
    • CInstruct the worker verbally and confirm the change with the Owner afterward by email
    • DEmail the instruction directly to the worker and keep a copy on the project file
    Show answer & explanation

    Correct answer: Decline, and route it through the Contractor/CM in writing (RFI or SI)

    The architect must not instruct trades directly. Doing so breaks the contractual chain of command, intrudes on the Contractor's/CM's responsibility for means and methods, and exposes the architect to liability. The correct path is to communicate with and through the Contractor or Construction Manager and to document any clarification or interpretation in writing (e.g., via RFI response or Supplemental Instruction).

  4. Question 4Theme 12

    A project meeting agenda item reads: 'Contract Schedule — 3 weeks behind on structural steel due to shop drawing revision cycle.' The most appropriate project management response is:

    • ANote it in the minutes and monitor for further delays at the next meeting, since a 3-week slip in steel is normally absorbed by float
    • BIssue a change order to accelerate the steel trade at the owner's cost
    • CInform the owner that the project will now be 3 weeks late and adjust the milestone dates
    • DCheck the critical path impact, find the cause and responsible party, and plan recovery
    Show answer & explanation

    Correct answer: Check the critical path impact, find the cause and responsible party, and plan recovery

    A schedule delay requires a structured response: determine if the activity is on the critical path, identify the root cause (design error, owner delay, contractor default), determine who bears the cost, and develop a mitigation plan. Simply noting it in the minutes without action is not adequate project management.

  5. Question 5Theme 13

    An architect is asked by a developer client to sign and seal drawings that were prepared entirely by another architect, without any review or involvement. The appropriate response is to:

    • AForward the drawings to the provincial association for approval before stamping, so that its review covers the architect's responsibility
    • BRefuse — an architect may only stamp documents they prepared or directly supervised
    • CSign and seal the drawings — the client takes full responsibility
    • DSign and seal with a note that the drawings were prepared by another, unregistered party
    Show answer & explanation

    Correct answer: Refuse — an architect may only stamp documents they prepared or directly supervised

    An architect must only stamp documents that they prepared or that were prepared under their direct supervision. Stamping another architect's work without review is professional misconduct ('rubber stamping') and is prohibited by provincial architectural acts and codes of ethics. The architect would be assuming professional responsibility for work they didn't perform or review.

  6. Question 6Theme 9

    A contractor submits a bid that is significantly lower than all others — so low it appears the contractor may have made an error. The owner should:

    • AAward the contract immediately to lock in the low price before other bidders react
    • BAccept the bid and hold the bidder to the stated price regardless of the error
    • CDisqualify the bid and re-tender the whole project
    • DNotify the bidder and let them withdraw before award without losing the bid bond
    Show answer & explanation

    Correct answer: Notify the bidder and let them withdraw before award without losing the bid bond

    Under the 'Contract A / Contract B' framework established by Ron Engineering, if a bidder makes an error, the owner may give the bidder the opportunity to withdraw before Contract B (the construction contract) is formed. Forcing execution of an erroneously low bid can result in poor-quality work or contractor insolvency.

  7. Question 7Theme 10

    An Owner moves into the entirety of a completed office building before all eight Ready-for-Takeover prerequisites have been met. Under CCDC 2 – 2020, what is the effect?

    • AThe Work is deemed to achieve Ready-for-Takeover, subject to the applicable lien legislation
    • BReady-for-Takeover cannot be attained until every prerequisite is satisfied
    • CThe Contract is deemed complete and the Contractor is released from further obligations
    • DThe Owner forfeits its warranty rights for the portions affected by the outstanding prerequisites
    Show answer & explanation

    Correct answer: The Work is deemed to achieve Ready-for-Takeover, subject to the applicable lien legislation

    GC 12.2.4 provides that if the Owner takes occupancy of the entirety of the Work before all the GC 12.1.1 prerequisites are met, the Work shall, subject to the requirements of the applicable lien legislation, be deemed to achieve Ready-for-Takeover. The same clause is explicit that this does not relieve the Contractor's responsibility to complete the Work in a timely manner. This is a deeming provision, not a waiver — warranty rights are unaffected.

  8. Question 8Theme 11

    An architect is preparing the certificate authorizing release of the statutory holdback that has accrued to the date of Substantial Performance. Per CHOP 6.7, which statement correctly describes this certificate and the funds it releases?

    • AThe certificate should be dated for payment one day after the termination of the lien claim period, and the holdback is a trust fund that cannot be used to compel the contractor to correct deficiencies
    • BThe architect should personally confirm with the land registry that no liens have been registered before issuing the certificate
    • CThe holdback release certificate must be issued before the certificate of Substantial Performance, since it authorizes the very funds that make Substantial Performance of the Work possible
    • DCertification of payment for known deficiencies is standard practice at this stage, since the holdback is a general contingency fund rather than a trust fund tied to specific invoiced amounts
    Show answer & explanation

    Correct answer: The certificate should be dated for payment one day after the termination of the lien claim period, and the holdback is a trust fund that cannot be used to compel the contractor to correct deficiencies

    CHOP 6.7 states the release-of-holdback certificate should be dated for payment one day after termination of the lien claim period, and that the holdback is a trust fund which "cannot be used to enforce the performance of the contractor nor to ensure that deficiencies are corrected" — certification of payment for known deficiencies should never be made until the work is acceptable. Confirming that no liens have been registered is a legal determination the chapter says the owner's lawyer, not the architect, should undertake; the architect only advises the owner to obtain that legal counsel.

  9. Question 9Theme 12

    A client-prepared agreement requires the architect to 'indemnify and defend' the client in any legal proceeding arising from the project. What is the specific risk management concern with the word 'defend'?

    • A'Defend' obliges the architect to fund the client's defence up front, which insurance generally won't pay
    • B'Defend' is a standard, fully insurable obligation equivalent to the indemnification obligation itself
    • C'Defend' only applies after a final judgment has been rendered against the client, so it adds no meaningful exposure
    • D'Defend' obligates the architect only to provide expert testimony on the client's behalf, at no cost to the architect
    Show answer & explanation

    Correct answer: 'Defend' obliges the architect to fund the client's defence up front, which insurance generally won't pay

    CHOP 3.8 states the architect should not agree to 'defend' the client in legal proceedings, because this is unlikely to be covered under the professional liability policy — insurance will generally only reimburse the client for a portion of legal fees, and only after negligence and damages have been established, not fund the defence up front.

  10. Question 10Theme 10

    A project carries three cash allowances. The lighting allowance is overspent, but the signage and landscape allowances are underspent by more than enough to cover the shortfall. How is this treated under CCDC 2 – 2020?

    • AThe Contractor is compensated for the excess on the lighting allowance plus overhead and profit on that excess
    • BThe Contractor absorbs the overspend, since cash allowances are fixed at bid closing
    • CThe Owner must issue a Change Order increasing the Contract Price by the amount of the overspend
    • DThe other allowances' unspent amounts are reallocated by the Consultant, with no added overhead and profit
    Show answer & explanation

    Correct answer: The other allowances' unspent amounts are reallocated by the Consultant, with no added overhead and profit

    GC 4.1.4 provides that where the actual cost under any cash allowance exceeds that allowance, unexpended amounts from other cash allowances shall be reallocated at the Consultant's direction to cover the shortfall, with no additional amount added to the Contract Price for overhead and profit. Only where the actual cost under ALL cash allowances exceeds the total of all cash allowances is the Contractor compensated for the excess plus overhead and profit on the excess only. Note also GC 4.1.2: the Contract Price, not the cash allowances, includes the Contractor's overhead and profit in connection with cash allowances.