Section 4 / Contracts

CCDC Cheat Sheet: One-Page Quick Reference for the ExAC

Published: April 25, 2026 Reading time: 9 min By: Issued for Interns

Section 4 of the ExAC tests heavily on CCDC contracts: which one fits which delivery method, what each one is for, who holds the trade contracts, and how the General Conditions actually function. Most candidates rate Section 4 the hardest section of the exam, and the CCDC suite is the largest reason why.

This is a one-page cheat sheet of every CCDC document tested on the ExAC, with a one-line memory hook for each. Use it as a final-week review reference, not as a substitute for reading the documents themselves.

Reading > memorizing. The ExAC tests judgment, not recall. Memorize this table for recognition speed under exam pressure, but make sure you've read the General Conditions of CCDC 2 in full at least twice.

The full CCDC suite at a glance

CCDC Document Delivery Price basis
CCDC 2 Stipulated Price Contract Design-Bid-Build Fixed lump sum
CCDC 3 Cost Plus Contract Negotiated / Emergency Actual costs + fee
CCDC 4 Unit Price Contract Civil / Tendered Unit rates × measured quantities
CCDC 5A CM: Services Only (Agency) CM Agency CM fee; Owner holds trades
CCDC 5B CM: Services and Construction CM at Risk CM fee + construction (often GMP)
CCDC 14 Design-Build Stipulated Price Design-Build Fixed lump sum (DB)
CCDC 15 Design-Build Cost-Plus Design-Build Actual costs + fee (DB)
CCDC 17 Stipulated Price for Trade Contractors CM / Multi-prime Fixed lump sum (trade)
CCDC 23 Guide to Calling Bids and Awarding Contracts Design-Bid-Build N/A: process guide
CCDC 30 Integrated Project Delivery IPD Target cost; shared risk/reward
CCDC 40 Rules for Mediation and Arbitration All N/A: dispute resolution
CCDC 41 Insurance Requirements All N/A: insurance schedule

One-line memory hooks

Which contract for which delivery method

ExAC scenario questions almost always describe a project situation and ask you to identify the correct delivery method and CCDC document. The decision hinges on a few key variables: schedule urgency, scope definability, owner sophistication, and whether the project is publicly funded.

Design-Bid-Build → CCDC 2

Default for fixed budget, defined program, no schedule urgency, public competitive tendering required. Most complete design resolution before construction; lowest risk from design changes. When in doubt on a "standard project with public funds," the answer is almost always Design-Bid-Build with CCDC 2.

Design-Build → CCDC 14 or CCDC 15

Repetitive project types (chain stores, schools, warehouses) where the Owner's program is reducible to an RFP. Single-point responsibility, faster overall schedule, but the architect is sub-contracted to the Design-Builder; owner loses independent design oversight. Use CCDC 14 when scope supports a fixed price; CCDC 15 when scope is still evolving.

Construction Management → CCDC 5A or 5B

The CM joins the team early to advise on schedule, cost, and constructability. Choose between 5A and 5B based on who holds the trade contracts:

Cost Plus → CCDC 3

Emergency stabilization, heritage restoration, or other situations where the scope of work is genuinely unknowable in advance. Three variants: Fixed Fee (no incentive to inflate cost), Percentage Fee (creates incentive to inflate; use with caution), and Cost-Plus with GMP/Upset Price (most common; caps total cost).

Unit Price → CCDC 4

Civil engineering and site work: roads, grading, underground utilities, where the type of work is well-defined but quantities are uncertain until excavation. Final contract amount determined by measured quantities verified by an independent inspector.

Integrated Project Delivery → CCDC 30

Large, complex, BIM-intensive projects where Owner, Architect, and key trade contractors collaborate from early design through completion. Shared Target Cost; if delivered below, all parties share savings; if above, all parties share losses up to a defined limit. Requires genuine trust and willingness to collaborate; IPD with adversarial parties fails.

The full Theme 9 chapter is free

Read our complete free chapter on Bidding, Delivery Methods & Contracts: every CCDC document explained with scenario examples and 25+ practice questions. No signup required.

Open the Theme 9 free chapter →

The bonds you must know

BondGuaranteesTypical amount
Bid Bond If accepted, the Contractor will sign the formal contract. Surety pays the difference between the bid and the next-lowest if Contractor fails to sign. 5–10% of estimated construction cost
Performance Bond Indemnifies Owner if Contractor defaults. Covers additional cost beyond the agreed contract amount. 50% or 100% of contract amount
Labour & Material Payment Bond Sub-contractors and suppliers with direct ties to the Contractor will be paid for labour and materials. Typically 50% of contract amount

Memory hook: Bid = "Before" (you'll sign). Performance = "During" (you'll finish). L&M = "Under" (those below you get paid).

Critical CCDC 2 numbers to memorize

Priority of Documents (GC 1.1.7): memorize this order

In case of conflict, from highest to lowest priority:

  1. Agreement
  2. Definitions
  3. Supplementary Conditions
  4. General Conditions
  5. Division 1 Specifications
  6. Technical Specifications
  7. Material/Finishing Schedules
  8. Drawings

Within the same type, later-dated documents take precedence over earlier ones. Larger-scale drawings govern over smaller-scale drawings of the same date.

Frequently asked questions

Which CCDC contract is most tested on the ExAC?

CCDC 2 (Stipulated Price Contract) is the most-tested CCDC document on the ExAC. It's the standard contract for Design-Bid-Build projects, which is itself the default delivery method tested in scenario questions. Within CCDC 2, the General Conditions, particularly priority of documents (GC 1.1.7), payment timelines (Part 5), and changes in the work (Part 6), are heavily tested.

What is the difference between CCDC 5A and CCDC 5B?

Both are Construction Management contracts. The critical difference is who holds the trade contracts. Under CCDC 5A, the Owner holds all trade contracts directly; the CM acts as adviser only. Under CCDC 5B, the CM holds the trade contracts directly, providing a single point of accountability. CCDC 5A suits sophisticated owners who want direct trade relationships; CCDC 5B suits fast-track projects where the owner wants single-point accountability without managing dozens of trade contracts.

Which CCDC document is used for Design-Build?

CCDC 14 is the Design-Build Stipulated Price Contract, used when scope is well-defined enough to fix a lump sum. CCDC 15 is the Design-Build Cost-Plus version, used when scope is not yet defined or an early construction start is needed before design is complete.

What does CCDC 23 cover on the ExAC?

CCDC 23 is the Guide to Calling Bids and Awarding Contracts. It governs the lowest-bid selection method under traditional Design-Bid-Build delivery. Key ExAC topics from CCDC 23: the two-contract model (Contract A / Contract B), the duty of fairness to all bidders, addenda procedures, the post-bid negotiation rules when bids exceed budget by less or more than 15%, and rejection of late or non-compliant bids.

What is CCDC 30?

CCDC 30 is the Integrated Project Delivery (IPD) contract. It's a multi-party agreement signed by the Owner, Architect, and key trade contractors, where all parties share risk and reward based on project outcomes. Used for large, complex, BIM-intensive projects where genuine collaboration justifies the contract complexity. Trust between parties is essential. IPD without real collaborative commitment fails.