Free Practice · Section 1 — Design

25 Free ExAC Practice Questions (Section 1 — Design)

By Issued for Interns Published May 13, 2026 25 questions · Interactive

The Examination for Architects in Canada (ExAC) is made of of four exams that are 3 hours each. Section 1 — Design is the first of the four sections, covering six of the thirteen ExAC themes: Programming, Site & Environmental Analysis, Engineering Systems, Cost Management, Schematic Design, and Design Development.

Although considered one of the more easier sections, Section 1 still requires a solid understanding of core design concepts and the ability to apply them to complex scenarios. The real exam emphasizes critical thinking and scenario-based questions rather than rote memorization. To succeed, candidates must be able to analyze unfamiliar situations, identify relevant principles, and make informed decisions based on their knowledge of architectural design and practice. Key tip: utilize the Canadian Handbook of Practice as well as Building Construction Illustrated.

Below are 25 free practice questions drawn directly from our full-length ExAC mock exam. Click any answer choice to reveal whether you got it right, along with a full rationale explaining the reasoning behind the correct answer. These questions reflect the format, difficulty, and content distribution of the real ExAC — including site analysis questions on reading contours and drainage. If contour lines and the rule of Vs are shaky, work through our guide to reading a topographic map for site design before you start.

Want the full 128-question timed mock exam? The complete Section 1 mock exam — 120 multiple-choice questions plus 8 short-answer questions, with a 3-hour timer and full scored review — is included with the ExAC Study Guide. Get the guide →

Ready for the full exam experience?

120 MCQ + 8 short-answer questions. 3-hour timer. Instant scoring and full rationale review. Same format as the real ExAC.

See the 2027 ExAC Study Guide →
Your Score
0 / 25 —
Practice Complete
—
Take the Full Mock Exam →

All 25 questions with answers and explanations

Every question from the quiz above, in the same order. Try each one, then open its explanation to see the correct answer and the reasoning behind it.

  1. Question 1Theme 1 — Programming

    Which of the following is the CLIENT's responsibility to provide at the start of a project — NOT the architect's?

    1. AFunctional program or design brief
    2. BFeasibility study
    3. CSite analysis and environmental review
    4. DPre-zoning assessment
    Show answer and explanation

    Correct answer: A. Functional program or design brief

    Per RAIC Document 6, the client is responsible for providing a program or design brief, the construction budget, and required reports such as surveys and specialist information. Feasibility studies, site analyses, and pre-zoning assessments are pre-design services performed by the architect — charged as additional services.

    Theme 1 — RAIC Document 6, Client Responsibilities

  2. Question 2Theme 1 — Programming

    The MacLeamy Curve illustrates a fundamental principle of design economy. What does it show?

    1. AConstruction costs rise steeply during design development and then level off once the project goes to tender
    2. BChange costs rise as the project advances while the ability to influence it falls
    3. CThe architect's fee should be front-loaded because most value is added at schematic design
    4. DMaterial costs are highest at the start of construction and lowest at completion, as procurement risk is retired
    Show answer and explanation

    Correct answer: B. Change costs rise as the project advances while the ability to influence it falls

    The MacLeamy Curve plots two lines: (1) the cost/effort to implement a design change, which rises steeply as a project advances; and (2) the architect's ability to influence cost and performance, which declines over time. Together they argue for front-loading design effort — investing more time in early phases when changes are cheap and impact is greatest.

    Theme 1 — MacLeamy Curve

  3. Question 3Theme 1 — Programming

    The five-step programming process bridges client needs to the design problem statement. In the correct sequence, the steps are:

    1. AFacts → Goals → Needs → Concepts → Problem
    2. BGoals → Facts → Concepts → Needs → Problem
    3. CNeeds → Goals → Facts → Concepts → Problem
    4. DGoals → Concepts → Facts → Needs → Problem
    Show answer and explanation

    Correct answer: B. Goals → Facts → Concepts → Needs → Problem

    The standard programming sequence is: (1) Goals — establish what the client wants to achieve; (2) Facts — gather data about the project; (3) Concepts — explore organizational ideas; (4) Needs — translate goals into spatial and performance requirements; (5) Problem — synthesize into the design problem statement.

    Theme 1 — Five-Step Programming Process

  4. Question 4Theme 1 — Programming

    A Class D cost estimate is prepared during pre-design. Which of the following BEST characterizes this estimate?

    1. AAccurate to ±5% of tender price; used as the final pre-tender budget
    2. BAccurate to ±10%; based on a detailed elemental breakdown of all building systems
    3. CIndicative order-of-magnitude estimate; no more than a ±20% design allowance is required
    4. DPrepared by the quantity surveyor at schematic design using $/m² unit rates
    Show answer and explanation

    Correct answer: C. Indicative order-of-magnitude estimate; no more than a ±20% design allowance is required

    Per CHOP Appendix A, the Class D (Indicative) estimate is prepared from a statement of requirements, outline solutions, and/or functional program — before schematic design begins — in elemental analysis format, to rank project options. Its level of accuracy is such that no more than a 20% design allowance is required. It serves only to confirm the project is in the right order of magnitude for the client's budget.

    Theme 1 — Cost Estimate Classes

  5. Question 5Theme 1 — Programming

    The traditional life-cycle cost ratio for a building is often cited as 1 : 5 : 200. What do these three numbers represent?

    1. ALand : Construction : Financing costs
    2. BDesign fees : Construction cost : Lifetime operating and maintenance costs
    3. CSchematic design : Design development : Construction documents effort
    4. DHard costs : Soft costs : Lifecycle replacement and renewal costs
    Show answer and explanation

    Correct answer: B. Design fees : Construction cost : Lifetime operating and maintenance costs

    The 1:5:200 ratio represents design fees : construction cost : lifetime operating and maintenance costs. For every dollar spent on design, approximately five dollars are spent constructing the building, and approximately two hundred dollars are spent operating and maintaining it over its lifetime. This ratio underscores the disproportionate leverage that design decisions have on long-term ownership costs.

    Theme 1 — Life-Cycle Cost Ratios

  6. Question 6Theme 2 — Site & Environmental Analysis

    For optimal passive solar performance, a building's long axis should be oriented:

    1. ANorth-south, to maximize exposure of all façades to direct sun
    2. BEast-west, so the largest façades face south and north for solar control
    3. CDiagonal at 45° to the cardinal directions, to balance morning and afternoon sun
    4. DPerpendicular to prevailing winds, regardless of solar orientation
    Show answer and explanation

    Correct answer: B. East-west, so the largest façades face south and north for solar control

    Orienting the long axis east-west places the largest building façades facing south (solar gain in winter, controlled with overhangs in summer) and north (minimal direct sun, diffuse light). This is the foundational principle of passive solar design in northern climates.

    Theme 2 — Building Orientation for Passive Solar

  7. Question 7Theme 2 — Site & Environmental Analysis

    Which shading device is MOST effective for controlling solar gain on east- and west-facing façades?

    1. AHorizontal overhangs, because they block the high summer sun
    2. BVertical louvers or fins, because they intercept the low-angle morning and afternoon sun
    3. CHorizontal light shelves, because they bounce daylight off the ceiling and deep into the floor plate
    4. DInsulated spandrel panels, because they eliminate glazing and its solar gain on those exposures
    Show answer and explanation

    Correct answer: B. Vertical louvers or fins, because they intercept the low-angle morning and afternoon sun

    East and west façades receive low-angle sun in the morning and afternoon, which horizontal overhangs cannot effectively block (the sun is too low in the sky). Vertical fins or louvers intercept this low-angle sun. South façades, where the sun is high in the sky at mid-day, are effectively shaded by horizontal overhangs.

    Theme 2 — Shading Devices by Façade Orientation

  8. Question 8Theme 2 — Site & Environmental Analysis

    In a cold climate, which of the following is the BEST location to site a building on a hillside?

    1. AAt the hilltop — maximum sun exposure, long views and good drainage away from the walls
    2. BOn the north-facing slope — protected from summer overheating and glare
    3. COn the mid south-facing slope — sheltered from north winds, maximizes solar gain
    4. DAt the valley floor — sheltered from wind and close to water and road access
    Show answer and explanation

    Correct answer: C. On the mid south-facing slope — sheltered from north winds, maximizes solar gain

    Mid south-facing slopes are the optimal cold-climate siting position: they face toward the sun (maximizing solar gain), are sheltered from prevailing cold north and west winds by the hill, and avoid cold air pooling at the valley floor (cold air drains downhill). Hilltops are exposed to maximum wind; valley floors collect cold air drainage.

    Theme 2 — Siting in Cold Climates

  9. Question 9Theme 2 — Site & Environmental Analysis

    The urban heat island effect is caused primarily by which of the following conditions?

    1. AHigh-rise buildings blocking wind and trapping vehicle exhaust gases at street level, where heat builds up
    2. BDark, impervious surfaces absorbing and re-radiating solar heat, with little vegetation
    3. CIncreased population density generating more metabolic and appliance heat than rural areas
    4. DReflected radiation from glass curtain walls heating adjacent streets
    Show answer and explanation

    Correct answer: B. Dark, impervious surfaces absorbing and re-radiating solar heat, with little vegetation

    The urban heat island effect results primarily from dark, impervious surfaces (asphalt roads, black roofs) that absorb solar radiation and re-radiate heat, combined with a lack of vegetation for evapotranspiration cooling. Mitigation strategies include high-albedo (reflective) surfaces, green roofs, and urban trees.

    Theme 2 — Urban Heat Island Effect

  10. Question 10Theme 2 — Site & Environmental Analysis

    A site is 3,500 m² in area. The zoning bylaw permits a maximum Floor Area Ratio (FAR) of 2.5. What is the maximum allowable gross floor area?

    1. A1,400 m²
    2. B6,000 m²
    3. C8,750 m²
    4. D10,500 m²
    Show answer and explanation

    Correct answer: C. 8,750 m²

    FAR = Gross Floor Area ÷ Site Area. Rearranged: Max GFA = FAR × Site Area = 2.5 × 3,500 = 8,750 m². This is a straightforward application of the FAR formula used in early design to determine maximum buildable area within zoning limits.

    Theme 2 — Floor Area Ratio Calculation

  11. Question 11Theme 3 — Engineering Systems

    Which of the following is classified as a DEAD load on a building structure?

    1. AThe weight of occupants and their furniture
    2. BAccumulated snow on the roof
    3. CThe self-weight of the concrete floor slab
    4. DWind pressure on the building façade
    Show answer and explanation

    Correct answer: C. The self-weight of the concrete floor slab

    Dead loads are permanent, static loads that do not change over the life of the building — primarily the self-weight of the structural system, floors, walls, and permanently fixed components. Live loads include occupants and furniture (variable). Snow and wind are environmental loads treated as live or dynamic loads in structural design.

    Theme 3 — Structural Loads: Dead vs. Live

  12. Question 12Theme 3 — Engineering Systems

    A floor beam sags visibly under load but does not crack or fail. This is best described as a problem of:

    1. AStrength — the beam's material is yielding beyond its allowable stress limit
    2. BStability — the beam is at risk of lateral-torsional buckling
    3. CStiffness — the beam is deflecting excessively while remaining structurally sound
    4. DSynergy — the structural system is not complementing the project's architectural intent
    Show answer and explanation

    Correct answer: C. Stiffness — the beam is deflecting excessively while remaining structurally sound

    Stiffness controls deformation under load. A beam that sags excessively but has not cracked or failed has adequate strength but insufficient stiffness. Stiffness failures manifest as excessive deflection that may damage finishes or create unacceptable serviceability conditions — even when the member is strong enough not to break.

    Theme 3 — Four Ss: Stiffness vs. Strength

  13. Question 13Theme 3 — Engineering Systems

    At what temperature does structural steel begin to lose its load-bearing capacity significantly — requiring fire protection in most building types?

    1. A200°C
    2. B350°C
    3. C520°C
    4. D800°C
    Show answer and explanation

    Correct answer: C. 520°C

    Structural steel begins to lose significant strength and stiffness at approximately 520°C. Building fires can easily exceed this temperature, which is why the National Building Code of Canada requires fire protection (spray-applied fireproofing, intumescent paint, or enclosure) for exposed steel in most occupancies above a certain size and height.

    Theme 3 — Steel: Fire Performance

  14. Question 14Theme 3 — Engineering Systems

    Which HVAC system type is most commonly used in large office buildings in Canada, and is characterized by varying the volume of conditioned air delivered to each zone?

    1. AFan coil unit system
    2. BVariable Air Volume (VAV) system
    3. CInduction (induction-unit) system
    4. DConstant Volume single-duct system
    Show answer and explanation

    Correct answer: B. Variable Air Volume (VAV) system

    Variable Air Volume (VAV) systems are the most common HVAC system in Canadian commercial office buildings. They distribute conditioned air from a central air handler through ductwork and vary the volume delivered to each zone via VAV terminal boxes — providing zone-level temperature control while maintaining a single central plant.

    Theme 3 — HVAC System Types

  15. Question 15Theme 3 — Engineering Systems

    Heat transfer through a solid masonry wall from warm interior air to a cold exterior surface is an example of which heat transfer mechanism?

    1. AConvection
    2. BRadiation
    3. CConduction
    4. DEvaporation
    Show answer and explanation

    Correct answer: C. Conduction

    Conduction is the transfer of heat through direct molecular contact within a solid material — heat moves from the warm interior surface through the masonry mass to the cooler exterior face. Convection is transfer through fluid movement. Radiation transfers heat through electromagnetic waves. Evaporation involves phase change from liquid to vapour.

    Theme 3 — Heat Transfer Mechanisms

  16. Question 16Theme 4 — Cost Management

    Under the RAIC Fee Guide's typical breakdown of fees for a traditional project, which two phases together account for the largest combined share of the architect's total fee?

    1. ASchematic Design and Design Development
    2. BDesign Development and Construction Documents
    3. CConstruction Documents and Construction Administration
    4. DTender/Negotiation and Construction Administration
    Show answer and explanation

    Correct answer: C. Construction Documents and Construction Administration

    In the RAIC Fee Guide's Table 1, Construction Documents carries 50% of the fee and Construction Administration 22.5% — together 72.5% of the total. Schematic Design and Design Development are 12.5% each, so the two design phases together reach only 25%, and Tender adds 2.5%, so Tender with Construction Administration comes to 25%. CD is the most labour-intensive phase; CA is the longest. The fee is back-loaded.

    Theme 4 — RAIC Fee Guide, Table 1, Typical Breakdown of Fees Over Design Project Phases

  17. Question 17Theme 4 — Cost Management

    The cost estimate prepared at Design Development is:

    1. AClass A (±5%) — final pre-tender estimate using elemental costs
    2. BClass D (±20%) — indicative estimate updated from pre-design
    3. CClass B or C (±10–15%) — more detailed than the SD estimate
    4. DNo estimate is required at DD — the SD estimate carries through to CD
    Show answer and explanation

    Correct answer: C. Class B or C (±10–15%) — more detailed than the SD estimate

    The DD estimate is Class B (±10%) or Class C (±15%), depending on the level of information available. It uses more detailed elemental costs than the SD area-method estimate and reflects the specific systems and assemblies being designed. It confirms budget alignment before the significant investment of CD production.

    Theme 4 — DD Cost Estimate

  18. Question 18Theme 4 — Cost Management

    A developer discusses three numbers: the 'construction budget,' the 'project budget,' and 'total project costs.' Which correctly describes the relationship between them?

    1. AThey are three different terms for the same number
    2. BConstruction budget ⊂ project budget ⊂ total project costs (each contains the previous)
    3. CTotal project costs are the sum of the construction budget and the project budget
    4. DThe project budget excludes land and financing costs, while the construction budget includes them
    Show answer and explanation

    Correct answer: B. Construction budget ⊂ project budget ⊂ total project costs (each contains the previous)

    The construction budget (bricks and mortar only) is a subset of the project budget (construction + land + design fees + permits + soft costs). The project budget is in turn a subset of total project costs, which adds operating, maintenance, and lifecycle costs over the building's lifespan.

    Theme 4 — Budget Hierarchy

  19. Question 19Theme 4 — Cost Management

    Value Engineering is most effectively applied at which project phase, and what is its primary goal?

    1. AConstruction Administration — to resolve value engineering changes proposed by the contractor
    2. BConstruction Documents — to reduce costs by simplifying detail drawings
    3. CSchematic Design — to find ways to cut cost while keeping the program and design quality
    4. DPre-design — to reduce the program so that it fits within the budget
    Show answer and explanation

    Correct answer: C. Schematic Design — to find ways to cut cost while keeping the program and design quality

    Value Engineering (VE) is most effective at Schematic Design, when the design is sufficiently defined to evaluate alternatives but not yet locked into detailed systems and specifications. VE's goal is to achieve equivalent function at lower cost — not by reducing quality or program, but by finding more economical means of meeting the same requirements.

    Theme 4 — Value Engineering

  20. Question 20Theme 4 — Cost Management

    Under the RAIC building category system, which group of building types correctly belongs to Category 6 (high complexity)?

    1. AWarehouses, garages, and agricultural buildings
    2. BStandard office buildings and retail stores
    3. CHospitals, courthouses, theatres, and art galleries
    4. DCustom single-family residences and legislative assembly buildings
    Show answer and explanation

    Correct answer: C. Hospitals, courthouses, theatres, and art galleries

    RAIC Category 6 includes complex, technically demanding institutional buildings: hospitals, laboratories, courthouses, theatres, art galleries, and similar facilities requiring extensive specialized systems and coordination. Category 1 covers simple utilitarian structures. Category 7 (highest) includes custom residences and unique civic buildings.

    Theme 4 — RAIC Building Categories

  21. Question 21Theme 6 — Schematic Design

    Per RAIC Document 6, what is the FIRST step in the schematic design process?

    1. APrepare schematic design drawings and a massing model
    2. BCheck that the client's program and budget are consistent
    3. CConduct the general building code overview with the AHJ
    4. DPrepare the Class C estimate of probable construction cost
    Show answer and explanation

    Correct answer: B. Check that the client's program and budget are consistent

    The schematic design process begins with reviewing the client's program and budget to confirm they are mutually consistent — that the programmed spaces can be accommodated within the available budget. Only after confirming this alignment does the architect proceed to code review, design, and estimating.

    Theme 6 — RAIC Doc 6 Clause 2.1: SD Process

  22. Question 22Theme 6 — Schematic Design

    What is the appropriate depth of building code analysis at the Schematic Design stage?

    1. AA full, detailed code review identifying all specific compliance requirements for every space
    2. BA general overview identifying major code constraints that will influence the design direction
    3. CNo code review — the AHJ performs all code analysis at permit application
    4. DA preliminary fire protection engineering report demonstrating life safety compliance for the AHJ
    Show answer and explanation

    Correct answer: B. A general overview identifying major code constraints that will influence the design direction

    Schematic design warrants only a general code overview — identifying the applicable codes, building classification, major occupancy constraints, and key zoning limits that will shape the design. Detailed code analysis (occupant loads, specific egress paths, unprotected opening calculations) is a Design Development deliverable.

    Theme 6 — Code Analysis at SD

  23. Question 23Theme 6 — Schematic Design

    The principle derived from the MacLeamy Curve that is most directly applied during Schematic Design is:

    1. AFast-tracking reduces overall project duration by overlapping phases
    2. BMore design effort and issue resolution at SD reduces the cost of later changes
    3. CThe architect should minimize SD fees to preserve budget for construction administration
    4. DMaterial specifications should be finalized at SD to avoid costly substitutions later
    Show answer and explanation

    Correct answer: B. More design effort and issue resolution at SD reduces the cost of later changes

    The MacLeamy Curve's core lesson — that design changes are cheapest early — is most directly applied by front-loading design effort at SD: resolving the structural system, orientation, program, massing, and major design decisions before proceeding to DD and CD, when changes become exponentially more expensive.

    Theme 6 — MacLeamy Curve Applied at SD

  24. Question 24Theme 7 — Design Development

    Schematic Design establishes WHAT the building will be. Design Development resolves:

    1. AWHO will build the building and under what contract form
    2. BWHEN the building will be built and the construction sequence
    3. CHOW the building will be constructed — the specific systems, assemblies, and materials
    4. DWHY the building program was chosen and how it meets the client's organizational goals
    Show answer and explanation

    Correct answer: C. HOW the building will be constructed — the specific systems, assemblies, and materials

    The key distinction between SD and DD is that SD defines the design concept (what the building is — form, organization, and systems strategy), while DD resolves the execution (how it will be built — specific structural system details, mechanical equipment, envelope assemblies, material selections). DD answers all 'how' questions before CDs are produced.

    Theme 7 — DD Purpose: SD vs. DD Distinction

  25. Question 25Theme 7 — Design Development

    A building is designed with operable windows near the floor and high-level vents near the ceiling to exhaust warm air during summer. This passive ventilation strategy relies on which physical principle?

    1. AThe Bernoulli effect — air pressure differential between high and low openings drives flow
    2. BThe stack effect — warm air rises and exits high, drawing cooler air in low
    3. CCross-ventilation — wind pressure drives air through the building from windward to leeward side
    4. DThermal mass — the slab absorbs warm air and moderates temperature swings
    Show answer and explanation

    Correct answer: B. The stack effect — warm air rises and exits high, drawing cooler air in low

    The stack effect (chimney effect) results from warm, less-dense air rising and exiting through high-level openings, creating a pressure differential that draws cooler outdoor air in at low levels. This is a fundamental passive summer cooling strategy. Cross-ventilation is wind-driven (horizontal); thermal mass moderates temperature by heat storage.

    Theme 7 — Passive Energy: Stack Effect

How did you do? Try the full 128-question mock exam.

All four ExAC sections. Full-length timed simulations. Instant scoring with theme-by-theme breakdown and detailed rationales for every question.

See the 2027 ExAC Study Guide →

Frequently Asked Questions

What does ExAC Section 1 cover?

Section 1 — Design covers six ExAC themes: Programming (Theme 1), Site & Environmental Analysis (Theme 2), Engineering Systems (Theme 3), Cost Management (Theme 4), Schematic Design (Theme 6), and Design Development (Theme 7). The exam includes 120 multiple-choice questions and 8 short-answer questions, with a 3-hour time limit.

How hard is the ExAC compared to these practice questions?

These practice questions are representative of actual ExAC difficulty — medium to hard. The real exam leans heavily on application and scenario-based reasoning rather than pure recall. Expect to apply concepts to unfamiliar situations, not just remember definitions.

Are mock exams available for Sections 2, 3, and 4?

Yes — mock exams for all four sections are now available and included with the ExAC Study Guide. Section 2 covers the National Building Code of Canada (NBC 2020) and NECB. Section 3 covers construction documents and specifications. Section 4 covers contracts, bidding, construction administration, and project management.

What is a passing score on the ExAC?

RAIC does not publish a fixed passing percentage — the exam is scored against a criterion-referenced standard set by the examination committee each cycle. As a benchmark, most candidates aim for 70%+ on practice materials to feel confident on exam day.

Is RAIC Document 6 heavily tested on Section 1?

Yes. RAIC Document 6 (the standard architect-client agreement) underpins much of the Schematic Design and Design Development content — phase definitions, fee structures, responsibilities, and cost estimation expectations. Understanding its clauses is essential for Sections 1 and 4.