Section 4 / Construction Administration

Site Instructions and Supplemental Instructions on the ExAC

Published: June 6, 2026 Reading time: 11 min By: Issued for Interns

During the construction phase, the architect's primary written tool for directing, clarifying, and correcting the work is the Supplemental Instruction. In practice, you'll also hear it called a Site Instruction, an Architect's Supplemental Instruction (ASI), or simply an SI. Under CCDC contracts, these are the same thing — and the ExAC tests your understanding of what they can and cannot do.

This is the document most candidates underestimate. It's not glamorous. It doesn't involve negotiating prices or resolving disputes. But it sits at the top of the change management hierarchy, and the ExAC uses it as the pivot point for an entire category of scenario questions: the architect just discovered something on site — what document do they issue first?

The answer almost always starts with a Supplemental Instruction. Whether it stays there depends on whether cost or time is affected.

What is a Supplemental Instruction?

A Supplemental Instruction (SI) is a written directive issued by the architect (or consultant) to the contractor during construction. It provides additional information, clarifies the contract documents, or directs a minor adjustment to the work — without changing the contract price or the contract time.

That last part is the key. An SI is explicitly limited to changes that have zero impact on cost and zero impact on schedule. The moment cost or time enters the picture, a different instrument is required.

CHOP (Canadian Handbook of Practice for Architects) Chapter 6.6 puts it plainly: if an SI involves changes to the contract price or to the contract time, the architect must then issue a Contemplated Change Notice or Proposed Change Notice, followed by either a Change Order or a Change Directive.

CCDC 24 — A Guide to Model Forms and Support Documents — goes further: it expressly prohibits architects from using Instructions to change elements of the contract. This is a common real-world mistake and a common exam trap.

What an SI can do

What an SI cannot do

The exam trap: A scenario describes the architect directing the contractor to install a different cladding material via a site instruction. The new material costs 12% more. The question asks whether the SI is valid. It is not — because the change affects the contract price. The correct answer is that a Contemplated Change Notice (CCN) must be issued first, followed by a Change Order once the price is agreed, or a Change Directive if work must proceed before agreement.

The change management hierarchy under CCDC 2

The ExAC tests your ability to pick the right instrument for the right situation. Here is the full hierarchy, from smallest to largest:

Instrument What it does Affects price? Affects time? Who signs?
Supplemental Instruction (SI) Clarifies, interprets, or directs minor adjustments No No Architect
Contemplated Change Notice (CCN) Alerts the contractor to a proposed change; requests pricing Anticipated Anticipated Architect
Change Order (CO) Formalizes agreed change to price and/or time Yes (agreed) Yes (agreed) Owner + Contractor
Change Directive (CD) Directs work to proceed before price agreement Yes (not yet agreed) Yes (not yet agreed) Owner

How to remember the flow

Think of it as an escalation ladder:

  1. SI — "No cost, no time, just clarity." The architect acts alone.
  2. CCN — "Something might change." The architect signals the contractor and asks for a price.
  3. CO — "We agree on the change." Both the owner and contractor sign off.
  4. CD — "We can't agree, but work can't wait." The owner directs the contractor to proceed; the price gets sorted out later.
Memory hook: SI is the architect talking. CCN is the architect asking. CO is everyone agreeing. CD is the owner directing.

The Contemplated Change Notice — the step most candidates skip

The Contemplated Change Notice (CCN) — also called a Proposed Change Notice (PCN) or Proposed Change (PC) in CCDC 24 — is the most misunderstood instrument in the hierarchy. It is not a change order. It is not an instruction to proceed. It is a formal notification that a change is being considered, paired with a request for the contractor to provide pricing.

The CCN exists for one reason: to give the contractor an opportunity to price the change before work proceeds. Without it, the architect risks issuing a Change Directive (which forces work to start before the price is agreed) or, worse, issuing an SI for a change that actually affects cost — which is contractually invalid.

When the CCN is required

What happens after the CCN

The contractor submits a quotation for the proposed change. If the owner and contractor agree on the price and any time adjustment, a Change Order is issued. If they cannot agree but the work must proceed to avoid delay, the owner issues a Change Directive — and the price is resolved later, often through the dispute resolution mechanisms in CCDC 2 (mediation, then arbitration under CCDC 40).

Change Order vs. Change Directive — the distinction the ExAC loves

This is one of the most frequently tested distinctions in Section 4. Both instruments modify the contract. The difference is consent.

Change Order (CO)

A Change Order is a written amendment to the contract, prepared by the architect, signed by both the owner and the contractor, stating their agreement on the change to the work, the adjustment to the contract price, and the adjustment to the contract time. It is a bilateral agreement — both parties must sign.

Key point for the exam: A Change Order requires mutual agreement. If the contractor refuses to sign because they dispute the price, you cannot issue a Change Order. You issue a Change Directive instead.

Change Directive (CD)

A Change Directive is a written instruction signed by the owner directing the contractor to proceed with a change in the work within the general scope of the contract documents, before the owner and contractor have agreed on adjustments to the contract price and the contract time.

A Change Directive exists because construction doesn't stop for negotiations. If water is coming through the foundation wall and the contractor needs to install a waterproofing membrane that wasn't in the original documents, you can't wait three weeks for a pricing negotiation. The owner directs the work to proceed; the price gets resolved afterward.

Key point for the exam: A Change Directive is signed by the owner, not the contractor. The contractor must comply — they don't get to refuse — but the price adjustment is determined after the fact. This is the critical difference from a Change Order.

The exam question pattern

A typical Section 4 scenario describes a situation where a change is needed on site. The answer choices usually include:

The trap is always the same: candidates who don't know the hierarchy pick the SI (because the architect issued it on site) or the Change Order (because it sounds like the final answer). The correct answer depends entirely on whether cost/time is affected and whether agreement has been reached.

The architect's authority on site — what you can and cannot direct

Under CCDC 2 (Part 2 — Administration of the Contract), the architect's role during construction is defined carefully. The ExAC tests this definition because candidates often confuse the architect's authority with the contractor's responsibilities.

The architect can:

The architect cannot:

The exam trap: A scenario asks what the architect should do when they observe the contractor using an incorrect construction method. The wrong answer is to direct the contractor to use a different method. The correct answer is to notify the contractor that the work does not conform to the contract documents and to reject the non-conforming work — but never to direct the means or methods of construction. That distinction is fundamental to CCDC 2 and is tested repeatedly.

RFIs and their relationship to SIs

A Request for Information (RFI) is issued by the contractor when the contract documents are unclear or insufficient. The architect must respond — typically within a time frame established in the supplementary conditions or the project manual.

The response to an RFI can take several forms:

CHOP Chapter 6.6 notes that some contractors abuse the RFI process by issuing excessive or frivolous RFIs — sometimes to transfer responsibility for decisions to the architect, to imply errors in the documents that don't exist, or to set up future delay claims. The architect must evaluate each RFI on its merits and respond appropriately without overreacting or under-documenting.

Concealed conditions — the 5-day rule

When the contractor encounters conditions that were not visible before construction and that differ materially from what the contract documents indicated, they must give written notice within 5 working days (GC 6.4 of CCDC 2). This triggers the concealed conditions process:

  1. Contractor provides notice within 5 working days of discovery
  2. Architect investigates and determines whether the condition differs materially from what was anticipated
  3. If the condition requires a change, the architect issues a CCN
  4. Price and time adjustments are negotiated — Change Order or Change Directive
Exam tip: If the contractor fails to give notice within 5 working days, they may lose entitlement to additional cost or time. The ExAC tests this time limit specifically.

Quick reference — which document, when

Situation Correct instrument Why
Contractor asks for clarification on a detail — no cost impact SI (in response to RFI) No cost, no time — clarification only
Owner wants to upgrade lobby flooring material CCN → CO Cost will increase; get contractor pricing first
Architect discovers an error in the drawings — correction needed, will affect cost CCN → CO or CD Cost impact; negotiate or direct
Water infiltration discovered — must fix immediately, no time to negotiate CCN → CD Urgent; direct work now, settle price later
Contractor proposes substituting a comparable product at no additional cost SI No cost, no time — if truly equivalent
Shifting a partition 50mm to clear an existing duct — no cost impact SI Minor field adjustment, no contract impact
Contractor and owner disagree on the price of a change CD (if work must proceed) or continue negotiation No mutual agreement — cannot issue CO

What the ExAC is really testing

Section 4 doesn't test your ability to fill out forms. It tests whether you understand the logic of contract administration: who has authority to do what, in what sequence, and under what conditions. The change management hierarchy — SI → CCN → CO / CD — is the spine of that logic.

When you see a scenario question in Section 4, ask yourself three things:

  1. Does this change affect the contract price or contract time? If no — SI. If yes — you need a CCN first.
  2. Have the owner and contractor agreed on the price? If yes — Change Order. If no — Change Directive (if the work can't wait) or continue negotiating.
  3. Who is signing? SI = architect. CCN = architect. CO = owner + contractor. CD = owner.

Get those three questions right and you'll handle every site instruction and change management scenario the ExAC throws at you.

The full Section 4 breakdown is free

This article covers the change management hierarchy specifically. For the complete treatment of Section 4 — CCDC contracts, delivery methods, bonds, priority of documents, certificates of payment, substantial performance, and 25+ practice questions — read the full Theme 9 chapter, fully unlocked.

Open the Theme 9 free chapter →

Frequently asked questions

What is the difference between a site instruction and a supplemental instruction?

In Canadian practice under CCDC contracts, these terms refer to the same instrument. A "site instruction" is the informal term for a written direction given during a site visit; a "supplemental instruction" (SI) is the formal CCDC term. In AIA (American) contracts, the equivalent is called an "Architect's Supplemental Instruction" (ASI). Regardless of the name, the rule is the same: it cannot change the contract price or contract time.

Can the architect issue a change order?

The architect prepares the change order, but it must be signed by both the owner and the contractor. The architect does not sign it — they draft it on behalf of the owner. A change order requires mutual agreement between the parties to the contract (owner and contractor), which the architect is not.

What happens if the contractor disagrees with a supplemental instruction?

If the contractor believes an SI will actually affect cost or time, they should notify the architect in writing. The architect must then evaluate whether a CCN and subsequent Change Order or Change Directive is required instead. If the contractor proceeds with work under protest, they may later pursue a claim — but they cannot unilaterally refuse to follow the SI.

Is the 5-day notice period for concealed conditions tested on the ExAC?

Yes. GC 6.4 of CCDC 2 requires the contractor to provide written notice of concealed or unknown conditions within 5 working days of discovery. Missing this deadline can affect entitlement to additional cost or time. This is a specific fact the ExAC tests.

How does a Change Directive differ from a Change Order on the ExAC?

The key difference is consent. A Change Order is signed by both the owner and the contractor — they agree on the change, the price, and the time. A Change Directive is signed by the owner only and directs the contractor to proceed before agreement is reached. The contractor must comply with a Change Directive; they don't need to agree. The price is resolved afterward.