Section 4 / Construction Administration

Construction Change Directive: What It Is Under CCDC 2

Published: June 28, 2026 Reading time: 6 min By: Issued for Interns

If you searched "construction change directive," you found the right idea under a slightly American name. In Canada, the instrument you are looking for is the Change Directive, set out in GC 6.3 of the CCDC 2 (2020) Stipulated Price Contract. It is one of the tools the project team uses to keep a job moving when a change is needed but the owner and contractor have not yet agreed on what it costs or how much time it adds.

That timing gap is the entire point of a change directive, and it is exactly the distinction the ExAC likes to test. This post explains what a change directive is, who signs it, how it gets valued, and how it differs from a change order. For the full picture of every document in the change management chain, see our guide to site instructions and supplemental instructions on the ExAC.

What a change directive actually is

Under CCDC 2 (2020), a change directive is a written instruction prepared by the Consultant and signed by the Owner. It directs the contractor to proceed with a change in the work, within the general scope of the contract documents, before the owner and contractor have agreed on the adjustment to the Contract Price and the Contract Time.

Three things make it distinct:

In plain terms: the owner wants something done now, the parties have not finished negotiating the dollars, and the project cannot afford to wait. The change directive lets the work start while the accounting catches up.

Why Canadians drop the word "construction"

The term "construction change directive," often shortened to CCD, comes from the American AIA A201 General Conditions, Article 7. Under the AIA system, a CCD is signed by the owner and the architect, the contractor performs the work whether or not it agrees, and the architect makes an interim determination of cost if the parties cannot settle.

Canada runs on the CCDC suite instead, and the differences are worth knowing because the exam is written around Canadian documents:

If your study materials or your firm's templates use American language, this is the translation. We cover more of these cross-border differences in our ARE vs ExAC comparison.

Change directive vs change order

This is the comparison that shows up on Section 4. A change order is an agreed change. A change directive is a directed change where agreement comes later.

Change Order (GC 6.2) Change Directive (GC 6.3)
Agreement on price and time Agreed before the document is issued Not yet agreed; settled afterward
Prepared by Consultant Consultant
Signed by Owner and Contractor Owner only
Contractor proceeds After signing Promptly on receipt, before price is set
Use it when The parties have settled the cost and time The change must proceed now, or the parties cannot yet agree
The mental model that holds up under exam pressure: If everyone has shaken hands on the number, it is a change order. If the work has to start before the handshake, it is a change directive. A change directive is the answer when the question stresses urgency or an unresolved price.

How a change directive moves through its lifecycle

A change directive is a temporary instrument, not a permanent contract modification. Once the price and time are determined, it converts into a change order. The steps below show that progression:

  1. Change directive issued — Consultant prepares it; Owner signs and issues to the contractor.
  2. Contractor proceeds — Work begins promptly, regardless of any pricing disagreement.
  3. Costs tracked — Contractor records actual expenditures and savings attributable to the directive.
  4. Price and time valued — Parties determine the Contract Price adjustment using the cost categories in GC 6.3.
  5. Converted to change order — Once price and time are agreed, a formal Change Order signed by both owner and contractor replaces the directive.

How a change directive gets valued

Because the work proceeds before the price is agreed, CCDC 2 has to set the rules for valuing it after the fact. The adjustment to the Contract Price for work carried out by a change directive is determined on the basis of the net cost of the contractor's actual expenditures and savings attributable to the directive.

The 2020 edition tightened this up. It reorganized the categories of cost a contractor can charge and made clear that a cost is only recoverable if it contributes directly to carrying out the change directive. Chargeable categories include items such as wages of office personnel working in a technical capacity, costs and rentals for construction equipment, certain legal and auditing costs, and project-specific information technology. The 2020 edition also removed some categories that the 2008 version had allowed — including wages for staff preparing or reviewing shop drawings.

Exam takeaway: Valuation is cost-based, reconciled after the work, and tracks actual expenditures and savings — not a price negotiated up front.

Common mistakes to avoid

These are the trap doors candidates fall through:

The full change management picture is one article away

This article focuses on the change directive specifically. For the complete hierarchy — SI, CCN, Change Directive, Change Order — and the exam logic that determines which document to issue and when, read our site instructions and supplemental instructions guide. For fast recall on exam day, keep the CCDC cheat sheet and 50 high-yield flashcards close by, and read the full contracts theme free in our Theme 9 sample chapter.

Open the Theme 9 free chapter →

Frequently asked questions

Is a "construction change directive" the same as a CCDC change directive?

They describe the same concept, but the names belong to different contract systems. "Construction change directive" is the AIA A201 term used in the United States. Under the Canadian CCDC 2 contract, the same idea is called a change directive and appears in GC 6.3.

Who signs a change directive under CCDC 2?

The Consultant prepares it and the Owner signs it. The contractor does not sign the directive itself, although the work later becomes a change order that both the owner and contractor sign.

Does the contractor have to follow a change directive?

Yes. Once the contractor receives a change directive, it must proceed promptly with the change in the work. Disagreement about the eventual price does not pause the work.

How is a change directive priced?

On a cost basis. The Contract Price adjustment is the net cost of the contractor's actual expenditures and savings attributable to the directive, using the cost categories CCDC 2 (2020) sets out in GC 6.3.

When should you use a change directive instead of a change order?

When the change has to proceed before the owner and contractor have agreed on price or time — often because of urgency or an unresolved negotiation. If agreement already exists, use a change order.