Section 4 / Construction Administration

Bonds, Holdbacks, and Project Closeout: The Money and Paperwork That Bookend a Project

Published: August 22, 2026 Reading time: 10 min By: Issued for Interns

Most of your logged hours sit in the middle of a project. Design, construction documents, coordination, the long grind of getting a set ready to build. That is where interns spend their time, and it is where the ExAC experience areas put the most weight.

The ExAC has a habit of testing the two ends instead. The security an owner takes before the first shovel goes in the ground, and the money and documents that change hands after the last deficiency is fixed. Bonds, holdback, and closeout. You touch them rarely as an intern, which is exactly why they are easy marks to lose.

Here is the simplest way to hold all three in your head:

Once you see them as the bookends of a contract rather than three unrelated topics, the exam logic gets a lot simpler.

First, two contracts are running at the same time

This is the frame that makes everything below easier to read. On a typical building project there are two separate agreements in play, and they govern different relationships.

The Canadian Handbook of Practice puts it plainly: the scope of the architect's work during construction is set by both the construction contract (CCDC 2) and the client and architect agreement (RAIC Document Six). So the machinery sits in CCDC 2, and your job description for operating it sits in Document Six. Keep that split in mind and the rest falls into place.

Bonds: security at the front end

In plain terms: a bond is a financial backer standing behind the contractor.

A bond is a three party promise. The contractor is the principal, the owner is the obligee, and a surety (usually a specialty arm of an insurer) stands behind the contractor. If the contractor fails to do what it promised, the surety answers to the owner.

One thing trips people up: a surety bond is not insurance. It is closer to a line of credit. The surety expects to be paid back by the contractor for anything it pays out, so getting bonded is really a measure of the contractor's financial strength. That is the whole point of asking for one. A bond is the owner's evidence that a third party with money on the line has vetted the contractor.

There are three standard forms, all published by the Canadian Construction Documents Committee and refreshed in 2024, the first update since 2002:

The short version. The bid bond protects against a bidder backing out, the performance bond protects against the contractor not finishing, and the labour and material payment bond protects everyone the contractor owes.

Where the architect fits

In contract administration the architect obtains the bonds and insurance certificates from the contractor before construction starts and forwards them to the owner. You are confirming the security exists and is in the owner's hands. You are not the one underwriting it, and you do not guarantee the contractor's performance. The surety expects the contractor to reimburse anything it pays out, so a bond mostly reflects the contractor's financial standing, not the architect's judgment.

Holdback: the safety net that runs the whole way through

In plain terms: holdback is money the owner keeps back from every payment, as a cushion against unpaid subtrades and unfinished work.

Every province requires it under lien legislation, though the exact mechanics vary. In Ontario, under the Construction Act, the owner must retain a basic holdback of 10 percent from the value of every payment certified to the contractor. That money is not the owner's to spend. It accrues cumulatively as work proceeds and is held for the benefit of everyone further down the payment chain who might otherwise be left unpaid if the contractor runs into trouble.

The formula. Basic holdback = 10 percent of the value of work certified to date, held cumulatively. On a contract where $950,000 of work has been certified, the basic holdback sitting with the owner is $95,000.

For the full progress-claim math, the schedule of values, and how a certificate for payment gets built line by line, see our guide to applications for payment and holdback. This article picks up where that one leaves off: what releases the holdback, and what comes after.

The lien clock, and why the architect starts it

Holdback is released after the lien period expires, assuming no liens have been registered. In Ontario the clock runs like this:

  1. The architect issues the Certificate of Substantial Performance and it is published.
  2. Lien claimants have 60 days from publication to preserve a lien, meaning register it on title.
  3. They then have a further 90 days, after the last day the lien could have been preserved, to perfect it, meaning start a court action.
  4. If nothing is registered, the basic holdback can be released.

Notice who starts that clock. The architect's certificate is the trigger. That is real authority, and it is why the timing of substantial performance shows up so often on the exam. A separate, smaller finishing holdback follows the same pattern after Total Completion, released once its own lien period expires.

Prompt payment, and the 2026 change

Layered on top of all this is Ontario's prompt payment regime: once the owner receives a proper invoice it has 28 days to pay the contractor, who then has 7 days to pay its subcontractors, and so on down the chain, with disputes going to fast track adjudication through ODACC rather than straight to court. CCDC 2 (2020) was rewritten to line up with these timelines. See the payment and holdback guide linked above for the full day-by-day breakdown.

A current change worth knowing, because the exam keeps pace with the codes: effective January 1, 2026, Ontario made annual holdback release mandatory on all contracts, under amendments the Fighting Delays, Building Faster Act, 2025 made to the Construction Act. It used to be optional and limited to very large projects. Now, on each anniversary of the contract date, the owner publishes a notice and releases the accrued holdback, which then starts building again from zero for the next year. Our roundup of what changed for 2026 tracks this kind of update.

Project closeout: the long tail at the end

Here is the misconception that costs marks: people treat substantial performance as the finish line. It is not. It is the point where the building is ready to be used for its intended purpose and the cost to finish the leftover work falls under a prescribed threshold. There are almost always deficiencies still on the list at substantial performance. Closeout is the sequence of milestones that takes you from usable to finished and signed off.

Under CCDC 2 (2020), the closeout sequence has three steps worth separating cleanly.

MilestoneCCDC 2 (2020) referenceWhat it triggers
Substantial Performance of the WorkDefined by lien legislation; payment under GC 5.4Release of the basic holdback; start of the lien period
Ready for TakeoverGC 12.1One year warranty; insurance period; Contract Time end date; indemnification; waiver of claims
Total / Final CompletionFinal certificate for paymentRelease of the finishing holdback; final payment

1. Substantial Performance of the Work

Defined by the applicable lien legislation, not by the contract itself. This is the milestone that releases the basic holdback and starts the lien clock described above. The architect certifies it. Deficiencies are expected and get tracked on a list to be completed or corrected.

2. Ready for Takeover

This is the milestone most older study material misses, and it is a favourite for a tricky question. CCDC 2 (2020) introduced Ready for Takeover, General Condition 12.1, as a new milestone that comes after substantial performance and before total completion. Before declaring it, the consultant confirms a set of conditions, including:

The contractor applies for it and the consultant has 10 days to respond. Ready for Takeover is now the trigger for the Contract Time end date, the one year warranty, the insurance period, indemnification, and waiver of claims. All of those used to hang off substantial performance.

The distinction the exam wants. Ready for Takeover does not replace substantial performance as the trigger for holdback release. Holdback still follows substantial performance and the lien legislation. So on a current CCDC 2 project you have two certificates doing two separate jobs: substantial performance releases the money, Ready for Takeover starts the warranty clock.

There is also an early occupancy path. If the owner takes possession of part of the work before Ready for Takeover, that part is deemed taken over, responsibility for its care passes to the owner, and the warranty period for that portion starts from the occupancy date.

3. Total Completion and final payment

The last rung. The finishing work is done, the architect carries out the final review, the finishing holdback is released, and the final certificate for payment is issued. Record drawings get finalized if the contract calls for them.

The closeout document turnover

Closeout is as much an administrative event as a physical one. Before final payment the architect collects the documents the owner will live with for years afterward. Drawing on the OAA's Mastering the Business of Architecture, the turnover bundle typically includes:

A useful instinct on the exam: if a question asks what is missing or out of sequence at closeout, scan for one of these documents being released before it should be, or final payment being issued before the package is complete.

One terminology trap that follows you into closeout

Throughout construction and closeout the architect performs field review, which RAIC Document Six calls general review, and the two terms mean the same thing. You visit the work at intervals to determine whether it is in general conformity with the construction documents, and you report in writing. You do not inspect, and you do not supervise. Those two words describe a level of service the architect does not provide, and they belong to the contractor. Using them in a certificate, a site review report, or an agreement can expose you to liability for work you never undertook. See our full breakdown of general review vs inspection vs supervision for the complete distinction. For the change management documents that run alongside all of this during construction, see our guide to site instructions and the change hierarchy.

How this shows up on the ExAC

This material lives in Section 4 territory and the contract administration themes. The questions tend to cluster around a handful of distinctions:

If you are licensing in Ontario, you will meet every one of these again in the OAA Admission Course, which is mandatory for licensure and runs through eight modules on the regulatory and legal side of practice. The Construction Act, professional liability and architect contracts, bid theory and practice, and contract administration and general review all map straight onto this article. The OAA describes the Admission Course as a practical foundation rather than an exam prep course. The ExAC tests the national concept; the Admission Course grounds it in how Ontario actually runs. They reinforce each other.

To fold this into your prep, slot the contract administration material into the back half of your 12 week study schedule, then drill the numbers with the CCDC cheat sheet and the flashcards, which cover bonds and key timelines.

The numbers worth memorizing

The full picture is in the study guide

Bonds, holdback, and closeout sit inside Theme 9 (Bidding & CCDC Contracts) and Theme 10 (Construction Administration) in our ExAC study guide. For the payment cycle that drives holdback accrual, read our guide to applications for payment and holdback. For the change management documents that run alongside closeout, see site instructions and change directives.

Open the free study guide preview →

Primary references

Frequently asked questions

Does Ready for Takeover replace substantial performance?

No. They do different jobs. Substantial performance releases the basic holdback and starts the lien period. Ready for Takeover, introduced in CCDC 2 (2020), starts the one year warranty, the insurance period, and the Contract Time end date. Both certificates exist on a current project.

What is the difference between a performance bond and a labour and material payment bond?

A performance bond guarantees the contractor finishes the work and protects the owner. A labour and material payment bond guarantees subcontractors and suppliers get paid, protecting the owner from liens further down the chain. They are typically issued together, both usually at 50 or 100 percent of the contract price.

How is construction holdback calculated in Canada?

The basic holdback is 10 percent of the value of work certified in each progress claim, held cumulatively. If $950,000 of work has been certified, the basic holdback is $95,000. It is released once the lien period after the Certificate of Substantial Performance expires, provided no liens have been registered.

How long does an owner have to release holdback in Ontario?

After the Certificate of Substantial Performance is published, lien claimants have 60 days to preserve a lien and a further 90 days to perfect it. If nothing is registered, the basic holdback can be released. Since January 1, 2026, Ontario also requires annual holdback release on all contracts, so accrued holdback is released on each contract anniversary regardless of substantial performance.

Who governs bonds and holdback, CCDC 2 or RAIC Document Six?

CCDC 2 is the agreement between the owner and the contractor, and it is where bonds, holdback, substantial performance, and Ready for Takeover live. RAIC Document Six is the separate agreement between the client and the architect, and it defines the architect's duties to administer the CCDC 2 contract.